New York Construction Site Safety Code
PART 23
PROTECTION IN CONSTRUCTION, DEMOLITION
AND EXCAVATION OPERATIONS
(Statutory authority: Labor Law, §§27-a,
27, 29)
SUBPART 23-3
DEMOLITION OPERATIONS
23-3.1
Special approval required
23-3.2
General requirements
23-3.3
Demolition by hand
23-3.4
Mechanical methods of demolition
SUBPART 23-3
DEMOLITION OPERATIONS
Historical Note
Subpart (§§23-3.1 – 23-3.4) added, filed
May 30, 1972 eff. June 1, 1972.
Top^
§ 23-3.1 Special approval required.
Any method of demolition of any building or other structure not named or described in this Subpart shall not be used unless granted a special approval.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-3.2 General requirements.
(a) Preparations for the demolition
of any building or other structures. (1)
Before demolition is started, all glass
in the exterior openings of the building
or other structure to be demolished
shall be removed.
(2) Before demolition is started, all
gas, electric, water, steam and other
supply lines shall be shut off and
capped or otherwise sealed. In each such
case, the service or utility company
involved shall be notified in writing at
least 24 hours in advance of the start
of work on such lines.
(3) Where it is necessary to maintain
any gas, electric, water, steam or other
supply line during the demolition
operations, such lines shall be so
protected with substantial coverings or
shall be so relocated as to protect them
from damage and to afford protection to
any person. If such lines are to be
relocated, the service or utility
company involved shall be notified in
writing at least 48 hours in advance of
such relocation. In not more than one
normal working day the service or
utility company shall notify the
employer of the procedure to be followed
in performing such relocation and such
procedure shall be followed by the
employer.
(b) Protection of adjacent structures.
During the demolition of any building or
other structure, the employer performing
such demolition shall examine the walls
of all buildings or other structures
adjacent to the one which is to be
demolished. Such examination shall
include a determination of the thickness
and method of support of any wall of
such adjacent buildings or other
structures. Where there is any reason to
believe that an adjacent building or
other structure or any part thereof is
unsafe or may become unsafe because of
the demolition operations, such
operations shall not be performed until
means have been provided to insure the
stability and to prevent the collapse of
such adjacent buildings or other
structures. Such means shall consist of
sheet piling, shoring, bracing or the
equivalent.
(c) Barricades. Demolition sites shall
be fenced, barricaded or provided with
sidewalk sheds in compliance with this
Part (rule).
(d) Dust control. Provision shall be
made at every demolition site to control
the amount of airborne dust resulting
from demolition operations by wetting
the debris and other materials with
appropriate spraying agents or by other
means.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
(a) Application. The provisions of
this section shall not apply to
mechanical means of demolition.
(b) Demolition of walls and partitions.
(1) The demolition of walls and
partitions shall proceed in a systematic
manner and all demolition work above
each tier of floor beams shall be
completed before any demolition work is
performed on the supports of such floor
beams.
(2) Masonry shall not be loosened nor
permitted to fall in such masses as to
endanger the structural stability of any
floor or structural support which such
masonry may strike in falling.
(3) Walls, chimneys and other parts of
any building or other structure shall
not be left unguarded in such condition
that such parts may fall, collapse or be
weakened by wind pressure or vibration.
(4) Employers shall not suffer or permit
any person to work while such person is
standing on top of a wall or any similar
elevated structure of small area.
(5) In the demolition by hand of
exterior walls, all persons performing
such work shall be provided with safe
footing in the form of sound flooring or
scaffolds constructed and installed in
compliance with this Part (rule).
(6) Walls or partitions which are being
demolished by hand shall not be left
standing more than one story or 15 feet,
whichever is less, above the uppermost
floor on which persons are working. Such
walls or partitions shall be removed
before the aggregate area of the
openings in such floor exceeds 25
percent of the total floor area.
(c) Inspection. During hand demolition
operations, continuing inspections shall
be made by designated persons as the
work progresses to detect any hazards to
any person resulting from weakened or
deteriorated floors or walls or from
loosened material. Persons shall not be
suffered or permitted to work where such
hazards exist until protection has been
provided by shoring, bracing or other
effective means.
(d) Boarding of wall openings. Where
windows and other exterior wall openings
in buildings or other structures being
demolished are more than 25 feet in
height above the ground or grade level
and are within 20 feet of any floor
opening used for the removal of debris
from floors above, such windows and
other openings shall be solidly boarded
up during demolition operations to
prevent the accidental passage of
debris.
(e) Methods of operation. Where the
demolition of any building or other
structure is being performed by hand,
debris, bricks and any other materials
shall be removed as follows:
(1) By means of chutes constructed and
installed in compliance with this Part
(rule);
(2) By means of buckets or hoists; or
(3) Through openings in the floors of
the building or other structure in
compliance with this section.
(f) Access to floors. There shall be
provided at all times safe access to and
egress from every building or other
structure in the course of demolition.
Such safe means of access and egress
shall consist of entrances, hallways,
stairways or ladder runs so protected as
to safeguard the persons using such
means from the hazards of falling debris
or materials.
(g) Protection in other areas. Every
floor or equivalent area within the
building or other structure that is
subject to the hazard of falling debris
or materials from above shall be boarded
up to prevent the passage of any person
through such area, or shall be fenced
off by a substantial safety railing
constructed and installed in compliance
with this Part (rule) and placed not
less than 20 feet from the perimeter of
such floor opening or such area shall be
provided with overhead protection in the
form of tight planking at least two
inches thick full size, exterior grade
plywood at least three-quarters inch
thick or material of equivalent
strength.
(h) Demolition of structural steel by
hand. Steel construction shall be
demolished column length by column
length and floor by floor. Every
structural member which is being
dismembered shall not be under any
stress other than its own weight and
such member shall be chained or lashed
in place to prevent its uncontrolled
swinging or dropping. Large structural
members shall not be thrown or dropped
from the building or other structure,
but shall be carefully lowered. Where a
derrick is used in the demolition of
buildings or other structures of
skeleton steel construction, the floor
upon which the derrick rests shall be
completely planked over with planking of
adequate size. Where other methods are
used, the persons engaged in the
dismantling of structural steel members
shall be protected by solidly planked
flooring not less than two inches thick
full size or sound floor arches not more
than two stories or 30 feet, whichever
is less, below and directly under that
portion of any tier of beams where such
persons are at work.
(i) Demolition of floor arches. Before
demolishing any floor arch, debris and
other materials shall be removed from
such arch and from other adjacent floor
areas. Planks not less than two inches
thick by nine inches in cross-section
full size shall be provided for and
shall be used by the persons to stand on
while breaking down floor arches between
beams. Such planks shall be so located
as to provide safe supports for such
persons should the arches between the
beams collapse. Any open spaces between
such planks shall not exceed 16 inches.
(j) Floor openings. (1) Permissible
aggregate area. During the demolition of
any building or other structure by hand,
the aggregate area of openings in the
floor immediately beneath the floor
being demolished shall not exceed 25
percent of the total area of such floor.
(2) Required protection. (i) Every
opening used for the removal of debris
or materials on every floor not closed
to access, except the top working floor,
shall be provided with an enclosure from
floor to ceiling equivalent to that
afforded by planking not less than two
inches thick full size. Such enclosure
shall be solid except for portions
openable for loosening blocked debris.
Alternatively, the opening shall be
fenced off by a substantial safety
railing constructed and installed in
compliance with this Part (rule) and
placed not less than 20 feet from the
perimeter of such opening. Every opening
not used for the removal of debris or
other materials in any floor to which
access is permitted shall be protected
by a solid enclosure as described above,
by a substantial safety railing
constructed and installed at least two
feet from the perimeter of the opening
and otherwise in compliance with this
Part (rule) or such opening shall be
solidly planked over with planks not
less than two inches thick full size.
(ii) Openings in the top or working
floor more than 16 inches in least
dimension shall be protected on all
sides, except the side at which debris
or other materials is deposited, by a
substantial safety railing constructed
and installed at least two feet from the
perimeter of the opening and otherwise
in compliance with this Part (rule) or
by a rope not less than five-eighths
inch diameter or an equivalent chain
placed not less than two feet from the
perimeter of such opening. Such rope or
chain shall be not less than 36 inches
nor more than 42 inches above the floor
surface. That portion of any floor
opening adjacent to and immediately
below a point where persons are employed
in any work upon a wall or equivalent
structure shall be provided with solid
flooring not less than five feet in
width measured from the inside face of
such wall or equivalent structure. Such
flooring shall consist of planking not
less than two inches thick full size,
exterior grade plywood not less than
three-quarters inch thick or material of
equivalent strength.
(k) Storage of materials. (1) General.
(i) Materials shall not be stored on
catch platforms, scaffold platforms,
floors or stairways of any building or
other structure being demolished, except
that any such floor may be used for the
temporary storage of materials when such
floor is of such strength as to safely
support the load to be imposed.
(ii) Storage areas shall not interfere
with access to any stairway or
passageway used by any person as a means
of ingress or egress. Suitable
barricades shall be provided to prevent
stored materials from sliding or
rebounding into any area where any
person is located or passing. All
materials shall be safely piled in such
locations as will not interfere with any
work operations nor present any hazard
to any person employed at or frequenting
the demolition site.
(2) Storage of debris or materials in
cellars. When debris or materials are
stored in the cellar or basement of any
building or other structure being
demolished, such debris or materials
shall not be in piles which extend
higher than the top of the foundation
wall. The person in charge of the
demolition operations shall provide
sheet-piling, shoring, bracing or such
other means as may be necessary to
insure the stability of such foundation
walls and to prevent any such wall from
collapsing due to the pressure of the
accumulated debris or materials.
(l) Safe footing required. Any person
working above the first floor or ground
level in the demolition of any building
or other structure shall not be suffered
or permitted to use accumulated debris
or piled materials as a footing in the
performance of his work. Every person
shall be provided with safe footing
consisting of sound flooring, planking
not less than two inches thick full
size, adequately supported exterior
grade plywood at least three-quarters
inch thick or other material of
equivalent strength.
(m) Catch platform required. During the
demolition of any exterior masonry wall
or a roof from a point more than 75 feet
above the adjoining ground, grade or
equivalent level where persons are
exposed to falling debris, materials or
objects, a catch platform shall be
constructed and installed in compliance
with this Part (rule). Such catch
platform shall be located at a level not
more than 20 feet below the working
level.
Exceptions: (1) A catch platform is not
required where a chimney is being
demolished.
(2) A catch platform is not required
where a scaffold, constructed and
installed in com-
pliance with this Part (rule), provide
equivalent protection.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-3.4 Mechanical methods of demolition.
The use of a swinging weight attached
to the line of a crane boom, clamshell
bucket, power shovel, bulldozer or any
other mechanical device or equipment for
the purpose of demolishing a building or
other structure or any remaining portion
thereof shall be in accordance with the
following requirements:
(a) Height limitation. The building or
other structure or any remaining portion
thereof shall be not more than 80 feet
in height above the ground, grade or
equivalent surface.
(b) Structural stability. Walls,
chimneys and other parts of any building
or other structure shall not be left
unsupported or unguarded in such
condition that such parts may fall,
collapse or be weakened by wind pressure
or vibration.
(c) Zone of demolition. (1) Where a
swinging weight is used in demolition
operations, a zone of demolition with a
radius of at least equal to one and
one-half times the height of the
building or other structure or any
portion thereof being so demolished
shall be maintained around the points of
impact. Where a swinging weight is used,
the supporting cables shall be of such
length or shall be so restrained that it
is not possible for the weight to swing
against any other building or structure
than the one being demolished.
(2) Where a clamshell bucket is being
used in demolition operations, a zone of
demolition shall be maintained within 25
feet on both sides of the line of travel
of the bucket.
(3) Where other mechanical devices or
equipment are being used in demolition
operations, a zone of demolition shall
be maintained in the area into which the
building or other structure or any
portion thereof may fall. Such zone of
demolition shall equal at least one and
one-half times the height of the
building or other structure or any
portion thereof above the ground, grade
or equivalent level.
(4) Only persons essential to the
operation of the demolition devices or
equipment shall be suffered or permitted
to enter any zone of demolition.
(5) Substantial barricades constructed
and installed in compliance with this
Part (rule) shall be erected wherever
there is likelihood of any person
entering a zone of demolition other than
the persons essential for operation of
the demolition devices or equipment.
(6) The controls of any mechanical
device or equipment used in demolition
operations shall be located and operated
a safe and reasonable distance from the
point of demolition.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
New York City Slip and Fall Attorneys
New York Accident Lawyers